 |
|
|
|
|
|
 |
|
| |
|
Bowery Bay WPCP WP-237
Interim Plant Upgrading
Queens, New York
Subconsultant
to Hazen and Sawyer, P.C.
|
|
Chu
& Gassman has and continues to provide electrical
design, construction sequencing, construction
management, inspection and operational assistance
services to Queens County, Bowery Bay Wastewater
Treatment Facility, located in Queens, New
York. The complete plant upgrade and renovation
has involved multiple phases of construction
with several contracts per phase over a period
of 15 years.
The Bowery Bay project consisted of many phases
of electrical, mechanical and instrumentation
work including but not limited to, the following:
Replacement of entire HVAC systems for existing
facilities and new system for Residuals Building
and Service Building including design of 4-750
hp boilers, pumps, piping, and instrumentation
system. HVAC system included replacement of
40 heating and ventilating units of total
capacity of 750,000 cfm.
The electrical distribution system is to be
extensively modified with the replacement
of a 208 volt system with a modern 480 volt
system. New 5kV switchboard and controls for
the plant's main process air blowers (8 @
1250 hp each) are to be provided. The main
sewage pump controls will be modernized to
utilize adjustable frequency drive (5 @ 800
hp).
Rehabilitation to the Con Edison service substation
will be provided. Old air magnetic 5kV circuit
breakers are to be replaced with modern vacuum
breaker designs.
All electrical equipment will be monitored
from a central control room. New air-conditioned
control rooms will be provided to contain
the plant's electrical equipment in order
to minimize the corrosion attendant to the
plant's proximity to the marine environment.
|
|
| Personnel |
Client
Contact |
|
|
HVAC
Abraham Y. Ago
Dave Bhatia
Stanley Chan
Michael LaPilusa
Andrew Lu
Joseph S. Masucci
Electrical
William
Gassman
Raghbir S. Bisal
Leonard W. Kurkewicz
Brian J. Martin
|
|
| Cost |
|
$212,000,000
$30,000,000 (HVAC)
$48,000,000 (E) |
|
| Completed
|
|
| 1998
(Design) |
| |
|
Mr.
Jerry Lastihenos
Senior Vice President
Hazen and Sawyer, P.C.
498 Seventh Avenue, 11th Floor
New York, New York 10018
(212) 777-8400 |
|
| |
| |
|
Hunts Point WPCP
New York, NY
City of New York Department of Environmental
Protection
Elmhurst, NY
Subconsultant
to URS Consultants
|
|
|
Chu
& Gassman provided the electrical and HVAC
Preliminary Design for a Contact Stabilization
Program Study and Report completed in 1992.
Additional Facility Planning for Comprehensive
Interim Upgrading (Task 10) included Final
Report, Preliminary Design Report, Outline
Specifications and was completed in 1997.
Construction Phase I includes, in general,
all improvements required to meet SPDES
permit or other regulations identified in
the Final Summary Report as follows:
- Main Building Improvements
- Chlorination Building Improvements
- Central Heating Facility
- Interim Heating Facility
- Site Hot Water Distribution System
- Central Residuals Facility
- Primary Scum Pumping Stations
- Primary Sludge PS Improvements
- Effluent Water PS Improvements
- Main Building Personnel Addition
- Aeration Operating Gallery Improvements
- Aeration Buildings Improvements
- Piping Tunnels Improvements
- New Plant Power Distribution System consisting
of three (3) 4160-480V unit substations,
new ductbank system, 20 new motor control
centers
- New Plant-Wide Instrumentation Control
System
Construction Phase II will include in general
all remaining improvements identified in
the Final Summary Report.
- New Service Entrance Electrical Substation
consisting of six (6) 13.2 k
feeders
and six (6) 7.5 MVA transformers, new distribution
switchgear with synch bus and
reactors.
- New emergency generator system consisting
of six (6) 2-MW diesel engine generators.
Construction Phase III will include the
Digester Gallery, Sludge Storage Tank Gallery
and the Thickener Odor Control Building.
Construction Phases II and III are in progress.
|
|
| Personnel |
Client
Contact |
|
|
Electrical
William Gassman
Frank
Carnovale
R. Keith Craven
HVAC
Jon
T. Chu
Abraham Y. Ago
Dave Bhatia
Mike LaPilusa
Joseph S. Masucci
|
|
| Cost |
|
$230,000,000
$75,000,000 (E/HVAC) |
|
| Completion
|
|
| 2006 |
| |
|
Mr.
Ernest Christbacher
URS Greiner
Mack Center II
Mack Center Drive
Paramus, NJ 07652-3095
(201) 262-7000 |
|
| |
| |
|
Project WP-284
New York City Sludge Dewatering Facilities
Wards Island, Hunts Point, Jamaica, 26th Ward,
Oakwood Beach, Bowery Bay
City of New York
Department of Environmental Protection
Subconsultant
to Hazen and Sawyer, P.C.
|
|
Chu
& Gassman provided electrical engineers and
inspectors to assist in construction management,
electrical inspection and testing services
for NYC DEP Sludge Dewatering Project Sites:
Wards Island, Hunts Point, Jamaica, 26th Ward,
Oakwood Beach, and Bowery Bay.
Engineers field tasks included: Cost estimates,
negotiations, justification of design changes,
issuance of change order requests, issue of
field sketches, verification of payments to
contractors, maintenance of documents, inspection
indexes, and maintenance of record set of
Contract Drawings. |
|
| Personnel |
Client
Contact |
|
|
Khondker
Ahmed
Joseph Alonso
Jay Andrews
James Duffy
Daniel Karvelas
Edwin Lazovick
James Machuga
Juris F. Millers
Andreas Paphitis
Semyon Peltz
Daniel A. Puszka
Steven Rimoli
|
|
| Cost |
|
| $246,000,000
|
|
| Completed
|
|
| 1994 |
| |
|
Mr.
Jerry Lastihenos
Senior Vice President
Hazen and Sawyer, P.C.
498 Seventh Avenue, 11th Floor
New York, New York 10018
(212) 777-8400 |
|
| |
| |
|
Red Hook WPCP WP-152
Contracts 8A and 12H
Manhattan, New York
City of New York
Department of Environmental Protection
Elmhurst, NY 11373
First Place Award - 1990
New York Association of Consulting Engineers
Subconsultant
to Hazen and Sawyer, P.C.
|
|
The
Red Hook Water Pollution Control Plant is
designed to treat an average dry weather wastewater
flow of 60 million gallons per day (mgd) and
a peak wet weather flow of 120 mgd. It is
a conventional, open-air facility, using step
aeration for full Secondary Treatment and
final disinfection to achieve an effluent
quality consistent with regulatory standards
(85% removal of pollutants).
Chu & Gassman provided electrical (including
fire/smoke alarm systems) and HVAC design
services for this project incorporating bio-gas
fired co-generating facilities, a tri-fueled
hot water generating plant. Modern computer
controls were utilized throughout. We also
provided start-up services for main pumps
and blower and main substation equipment and
control panels. |
|
| Personnel |
Client
Contact |
|
|
Jon
T. Chu
William Gassman
Dave Bhatia
Frank Carnovale
Esteban Cruz
C. Derrick Markham
Construction
John M. Burt
Juris F. Millers
|
|
| Cost |
|
$157,000,000
$37,000,000 (Electrical, HVAC) |
|
| Completed
|
|
| 1990 |
| |
|
Mr.
Jerry Lastihenos
Senior Vice President
Hazen and Sawyer, P.C.
498 Seventh Avenue, 11th Floor
New York, New York 10018
(212) 777-8400 |
|
|
|
|
|